Tunbridge-Wells 165 Aluminium Window Project

For this project, we changed all the windows in this office block, located at a property in Tunbridge-Wells. Focusing on the property’s aesthetics, thermal efficiency, and durability to refresh the appearance & functionality of the premises.

Get in touch

Tunbridge-Wells February 2025

The Project

BJH was tasked with transforming this entire building & its old, faulty windows & replace them with 165 AluK 58BW windows in black. This involved removing the existing, supplying, and installing the new windows.

 

The Product

All 165 windows used were the AluK 58BW Hi Casement, these aluminium windows offer exceptional durability & impressively low U-Values of 1.4 W/M ²K with double glazing. Each window had trickle ventilation conforming to government regulations.

For enhanced thermal performance, the AluK 58BW Hi Casement is also available with triple glazing, and Comfort Plus glass for even lower U-Values.

 

AluK58BW Features:

  • Tested to PAS 24
  • Green guide rated A
  • Deep head profiles for trickle ventilation
  • Polyamide thermal break design to improve thermal performance

 

Options:

  • Triple glazing
  • Various glass finishes, including Laminated and Comfort Plus
  • Secured By Design Certified
  • Internally or externally glazed
  • 58mm or 70mm frame depth
  • Single & dual colours, with anodised options
  • Flush design option
  • Multiple hanging configurations (e.g. top or side)
aluk

Safety

BJH Windows takes safety seriously. Ensuring all risk assessments & method statements were provided prior to the job commencing. With all our installation teams required to wear hard hats & safety vests throughout.

 

For high level work, the installation experts were given a 300kg safety weight, attached to inertia reels & harnesses to prevent any chance of accidents. Much of the safety equipment was sourced from Leach’s.

Adjacent paths and potentially dangerous zones below the building were blocked off with high visibility safety fencing. Ensuring any falling debris, would fall in a restricted area with no pedestrians.


        

Execution & Challenges

Our teams worked tirelessly, taking 165 windows & 330 pieces of toughened glass up & down multiple stories (with no working escalator!) in the relentless summer heat.

 

To minimise disruption on the active worksite, we completed the installation floor-by-floor. Our installation teams stayed overnight in a nearby hotel, maximising productivity. Thanks to the 2 teams’ dedication and efficiency, this job was completed in 6 weeks (30 working days).